| =====CNSI Innovation Workshop and Microfluidics Lab Battery Segment Manufacturing & Assembly Safe Operating Procedures===== | =====CNSI Innovation Workshop and Microfluidics Lab Battery Segment Manufacturing & Assembly Safe Operating Procedures===== | ||
| - | Last Updated: | + | Last Updated: | 
| This SOP provides a guide to safely manufacture and assemble battery segments of the GR23 electrical vehicle. Some of the information is compiled from the following sources. | This SOP provides a guide to safely manufacture and assemble battery segments of the GR23 electrical vehicle. Some of the information is compiled from the following sources. | ||
| * [[https:// | * [[https:// | ||
| Line 60: | Line 60: | ||
| ====Machining of insulation panels==== | ====Machining of insulation panels==== | ||
| - | - Fixture panels, program cam, and set up tools on ShopBot Router referencing [[http:// | + | - Fixture panels, program cam, and set up tools on ShopBot Router referencing [[http:// | 
| + | {{: | ||
| *Set up vacuum attachment and wear masks to minimize inhalation of fine fiberglass particles | *Set up vacuum attachment and wear masks to minimize inhalation of fine fiberglass particles | ||
| - File edges of panels to remove sharp glass fibers | - File edges of panels to remove sharp glass fibers | ||
| ====Assembly of Enepaq modules within insulation==== | ====Assembly of Enepaq modules within insulation==== | ||
| - | - Use epoxy to bond base and side panels of segment | + | - Insert modules with correct polarities and use epoxy to bond base and side panels of segment | 
| + | {{: | ||
| - **Wear proper PPE (listed in safety considerations section); those without PPE should remain five feet away** and connect modules together using bolts and busbars | - **Wear proper PPE (listed in safety considerations section); those without PPE should remain five feet away** and connect modules together using bolts and busbars | ||
| * **Cover work surface and ground with electrically insulating mat and use insulated tools** | * **Cover work surface and ground with electrically insulating mat and use insulated tools** | ||
| Line 71: | Line 73: | ||
| * Attach temperature sensing wires to module xr connector | * Attach temperature sensing wires to module xr connector | ||
| - Route wires through holes in top panel | - Route wires through holes in top panel | ||
| - | - Bond top panels to enclose segment | + |  | 
| + | {{: | ||
| + |  | ||
| + | {{: | ||